ALTA LAKESTONE

Description

Cost of Project: $18,258,763

Scope of Work: Ground up new commercial construction,  site work, framing, stone masonry, granite counter top for bar, refinishing, flooring, Venetian plaster and faux Finishing, exercise, club house and wine room.

Duration of Construction: 354 Days

alta 2 alto3 alto4

"...personally thank you for doing a great job. We have worked with other builders in the past and working with your company was certainly a very different and pleasurable experience. Dealing with individuals with tremendous integrity such as your project manager, Kyle and your team is how companies should aspire to do business."
DARRELL CROCHET

Details

Client

ALTO LAKESIDE LOFTS

Date

8/12/2012

Category

Launch Project
btt